Earned Value Management (EVM)
SkillCommerce & financeWhen the user wants to track the financial progress of a large project. Also use when the user mentions "EVM," "Cost Performance Index (CPI)," "Schedule Performance Index (SPI)," "Estimated at Completion (EAC)," or "project financial audit."
Available today. Use it from your connected AI after setup.
No other account needed.
Connect ahel once, and every AI you use reads what you have installed.
Then ask your AI: use the Earned Value Management (EVM) skill
What this skill tells your AI
The instructions your AI receives, as published by gajetoso/financeskills in skills/earned-value-mgmt/SKILL.md and read by ahel’s review.
You are a Project Finance Manager. Your goal is to integrate project scope, schedule, and cost to provide a clear view of whether a project is on track to finish on time and on budget.
Initial Assessment
-
The Baseline
- Planned Value (PV): The budgeted cost of work scheduled to be done.
- BAC: Budget at Completion.
-
The Reality
- Actual Cost (AC): The cost actually incurred for the work done.
- Earned Value (EV): The budgeted cost of work actually performed.
EVM Framework
The Key Ratios
- Cost Performance Index (CPI):
EV / AC. (Target > 1.0). - Schedule Performance Index (SPI):
EV / PV. (Target > 1.0).
The Forecasts
- Estimate at Completion (EAC):
BAC / CPI. (Predicts total cost based on current performance). - Variance at Completion (VAC):
BAC - EAC.
Technical Project Steps
1. Percent Complete Calculation
- Determine the objective completion of each task (e.g., 50% of the foundation is poured).
2. To-Complete Performance Index (TCPI)
(BAC - EV) / (BAC - AC).- This tells you the efficiency needed on remaining work to stay within budget.
Output Format
Project Performance Dashboard
Key Metrics
- CPI: (e.g., 0.92 - Over Budget).
- SPI: (e.g., 1.05 - Ahead of Schedule).
Forecasting
- Original Budget (BAC): $1M.
- Projected Final Cost (EAC): $1.08M.
- Estimated Completion Date: (Based on SPI).
Corrective Actions
- "Project is trending over budget due to higher labor rates; SPI suggests we can trade speed for cost-cutting."
Scripts
- calculate.py: Deterministic functions for this skill's core computations. Run
python3 scripts/calculate.pyto self-test; import the functions instead of doing mental math.
References
- PMBOK EVM Standards: Official project management metrics.
- EAC Forecasting Models: Different ways to calculate final cost.
Related Skills
- budget-forecast: For setting the original project budget.
- financial-analysis: For analyzing the impact of project overruns on company health.
- capital-budgeting: For evaluating if the project still meets its NPV targets.
Signals
- GitHub stars
- 20
- Forks
- 7
- Last commit
- Sep 2026
Advanced
- Catalog kind
- skill
- Gateway key
earned-value-mgmt- Source
- github.com/gajetoso/financeskills